BP to restart Ohio refinery by week's end following planned work - source
NEW YORK, July 18 (Reuters) - BP Plc plans to restart its 135,000 barrel-per-day refinery in Toledo, Ohio, by the end of the week following a plant-wide shutdown that began on May 9, according to a source familiar with the plant's operations.
The plant was scheduled to be shut down for roughly 70 days.
The refinery is a joint venture between BP and Husky Energy (Toronto: HSE.TO - news) .
(Reporting By Jarrett Renshaw; Editing by Chizu Nomiyama)