Advertisement
UK markets closed
  • FTSE 100

    8,213.49
    +41.34 (+0.51%)
     
  • FTSE 250

    20,164.54
    +112.21 (+0.56%)
     
  • AIM

    771.53
    +3.42 (+0.45%)
     
  • GBP/EUR

    1.1652
    -0.0031 (-0.26%)
     
  • GBP/USD

    1.2546
    +0.0013 (+0.11%)
     
  • Bitcoin GBP

    50,351.08
    +3,048.29 (+6.44%)
     
  • CMC Crypto 200

    1,359.39
    +82.41 (+6.45%)
     
  • S&P 500

    5,127.79
    +63.59 (+1.26%)
     
  • DOW

    38,675.68
    +450.02 (+1.18%)
     
  • CRUDE OIL

    77.99
    -0.96 (-1.22%)
     
  • GOLD FUTURES

    2,310.10
    +0.50 (+0.02%)
     
  • NIKKEI 225

    38,236.07
    -37.98 (-0.10%)
     
  • HANG SENG

    18,475.92
    +268.79 (+1.48%)
     
  • DAX

    18,001.60
    +105.10 (+0.59%)
     
  • CAC 40

    7,957.57
    +42.92 (+0.54%)
     

Operators award UK-Belgium power link contracts to Siemens, Sumitomo

LONDON, June 8 (Reuters) - Belgium's Elia and Britain's National Grid (LSE: NG.L - news) have awarded two contracts jointly worth roughly 500 million euros ($558.35 million) to build the first power trade cable between Britain and Belgium to Siemens (Xetra: SIEC.DE - news) and a subsidiary of Sumitomo Electric Industries.

Siemens will build and maintain the converter stations needed to transport the electricity, while Sumitomo Electric's J-Power Systems will manufacture and lay the 140-kilometre long subsea cable.

Construction work on the 1,000-megawatt project is expected to start later this year and the interconnector is set to start operating in 2019.

The so-called NEMO link will be the first electricity import-export cable to connect Britain and Belgium and is supported by financing from the European Commission as it is deemed a project of common interest to member states.

Network operators Elia and National Grid made a final investment decision to build the project in late February. ($1 = 0.8955 euros) (Reporting by Karolin Schaps)