Advertisement
UK markets close in 2 hours 2 minutes
  • FTSE 100

    8,072.88
    +28.07 (+0.35%)
     
  • FTSE 250

    19,766.77
    -32.95 (-0.17%)
     
  • AIM

    755.15
    +0.28 (+0.04%)
     
  • GBP/EUR

    1.1640
    +0.0012 (+0.10%)
     
  • GBP/USD

    1.2452
    0.0000 (-0.00%)
     
  • Bitcoin GBP

    53,065.20
    -13.11 (-0.02%)
     
  • CMC Crypto 200

    1,428.70
    +4.60 (+0.32%)
     
  • S&P 500

    5,070.55
    +59.95 (+1.20%)
     
  • DOW

    38,503.69
    +263.71 (+0.69%)
     
  • CRUDE OIL

    82.85
    -0.51 (-0.61%)
     
  • GOLD FUTURES

    2,332.70
    -9.40 (-0.40%)
     
  • NIKKEI 225

    38,460.08
    +907.92 (+2.42%)
     
  • HANG SENG

    17,201.27
    +372.34 (+2.21%)
     
  • DAX

    18,136.24
    -1.41 (-0.01%)
     
  • CAC 40

    8,127.61
    +21.83 (+0.27%)
     

Supreme Court stops Adani Power from charging higher prices

By Sudarshan Varadhan and Suchitra Mohanty

NEW DELHI (Reuters) - The Supreme Court ruled on Tuesday that Adani Power Ltd cannot charge its customers more to cover a surge in the cost of imported coal, overturning a decision by a power regulator in December.

The ruling sent Adani Power's shares down as much as 20 percent on Tuesday, its biggest intra-day loss since it went public in 2009.

The court did, however, allow the utility to claim relief for the higher costs, which resulted from a shortage in domestic supplies at state-run Coal India Ltd.

Both Adani Power and competitor Tata Power - which was also party to the ruling although it was not mentioned directly in it - struck long-term deals in the middle of the last decade with distribution companies to supply power from plants they each operate in Prime Minister Narendra Modi's home state of Gujarat.

ADVERTISEMENT

The companies also struck deals with domestic and foreign miners in the latter part of the last decade to fuel their plants in Gujarat, which each have over 4,000 megawatt (MW) of capacity.

LENGTHY LEGAL BATTLE

In 2010, Indonesia adopted new benchmark coal prices leading to an increase in the price of coal imported from the country.

Adani and Tata appealed for relief, arguing that they had to be compensated for an unforeseen change in economic conditions which made the terms of the deal with distribution companies unviable.

Following a legal battle that stretched over half a decade, the Central Electricity Regulatory Commission (CERC) ruled in December last year that the companies could charge their customers more to compensate for higher costs.

The case, which was argued by former minister and lawyer Kapil Sibal and renowned anti-corruption lawyer Prashant Bhushan among others, was then escalated to the country's top court by the state distribution companies.

The top court ruled in favour of the distribution companies, saying the agreements did not state that "coal is to be procured only from Indonesia at a particular price".

"The price payable for the supply of coal is entirely for the person who sets up the power plant to bear," the top court's judges said in Tuesday's ruling.

CERC will now look at the matter afresh and determine what relief should be granted to the companies to make up for the shortage in domestic coal supplies.

Companies will now be more cautious when entering into long-term power purchase agreements, a Mumbai-based analyst told Reuters.

Adani Power's shares recovered some losses on the day to close about 16 percent lower at 37.20 rupees. Shares in Tata Power closed down 1.8 percent at 85.45 rupees.

(Additional reporting By Darshana Sankararaman in Bengaluru; Editing by Subhranshu Sahu and Susan Fenton)