Advertisement
UK markets closed
  • FTSE 100

    8,139.83
    +60.97 (+0.75%)
     
  • FTSE 250

    19,824.16
    +222.18 (+1.13%)
     
  • AIM

    755.28
    +2.16 (+0.29%)
     
  • GBP/EUR

    1.1680
    +0.0023 (+0.20%)
     
  • GBP/USD

    1.2498
    -0.0013 (-0.10%)
     
  • Bitcoin GBP

    51,167.32
    -776.46 (-1.49%)
     
  • CMC Crypto 200

    1,330.94
    -65.59 (-4.70%)
     
  • S&P 500

    5,099.96
    +51.54 (+1.02%)
     
  • DOW

    38,239.66
    +153.86 (+0.40%)
     
  • CRUDE OIL

    83.66
    +0.09 (+0.11%)
     
  • GOLD FUTURES

    2,351.60
    +9.10 (+0.39%)
     
  • NIKKEI 225

    37,934.76
    +306.28 (+0.81%)
     
  • HANG SENG

    17,651.15
    +366.61 (+2.12%)
     
  • DAX

    18,161.01
    +243.73 (+1.36%)
     
  • CAC 40

    8,088.24
    +71.59 (+0.89%)
     

British gas storage site Rough to shrink capacity

Sept 9 (Reuters) - Capacity at Rough, Britain's largest natural gas storage site, will be permanently reduced, operator Centrica Storage Limited said on Friday, as it withdraws an offshore platform that operates four of Rough's approximately 30 wells.

Centrica (Frankfurt: A0DK6K - news) confirmed it expected to have 20 wells available for gas withdrawal at Rough from November 1 as planned as part of maintenance at the site.

Rough is a partially depleted North Sea gas field used for storage since 1985.

Centrica announced extended maintenance for the site's 47/8A platform in August 2015.

"Permanently withdrawing 47/8A from service will have a minimal impact on Rough's capabilities and CSL (Other OTC: CMXHF - news) has prepared for the possibility that it would never return to service," Centrica (Amsterdam: CC8.AS - news) said. (Reporting by Swati Verma in Bengaluru and Nerijus Adomaitis in Oslo; editing by Jason Neely)