Advertisement
UK markets close in 1 hour 56 minutes
  • FTSE 100

    8,119.99
    +41.13 (+0.51%)
     
  • FTSE 250

    19,783.86
    +181.88 (+0.93%)
     
  • AIM

    755.04
    +1.92 (+0.25%)
     
  • GBP/EUR

    1.1674
    +0.0017 (+0.15%)
     
  • GBP/USD

    1.2504
    -0.0007 (-0.05%)
     
  • Bitcoin GBP

    51,016.80
    +562.88 (+1.12%)
     
  • CMC Crypto 200

    1,381.73
    -14.81 (-1.06%)
     
  • S&P 500

    5,080.42
    +32.00 (+0.63%)
     
  • DOW

    38,122.13
    +36.33 (+0.10%)
     
  • CRUDE OIL

    84.29
    +0.72 (+0.86%)
     
  • GOLD FUTURES

    2,356.90
    +14.40 (+0.61%)
     
  • NIKKEI 225

    37,934.76
    +306.28 (+0.81%)
     
  • HANG SENG

    17,651.15
    +366.61 (+2.12%)
     
  • DAX

    18,084.54
    +167.26 (+0.93%)
     
  • CAC 40

    8,062.91
    +46.26 (+0.58%)
     

First subsea cables laid in £660m project to connect Shetland to energy grid

The NKT Victoria has begin laying the cables that will connect Shetland to Britain’s energy system for the first time (SSEN/PA)
The NKT Victoria has begin laying the cables that will connect Shetland to Britain’s energy system for the first time (SSEN/PA)

A £660 million project which will connect Shetland to the main British energy system for the first time has passed a major milestone.

Scottish and Southern Electricity Networks (SSEN) announced the first phase of cable-laying as part of the Shetland High-Voltage Direct Current (HVDC) Link is now under way off the coast of Caithness.

When completed, the subsea cable will connect Shetland to the UK energy system, in a move which will provide security of supply for islanders but will also benefit renewable energy projects in and around the islands.

The specialist vessel NKT Victoria has begun laying the first 100km of cable on the seabed – work which is expected to be completed by the middle of July.

ADVERTISEMENT

This is taking place after boulders were moved from the cable route to create a clear pathway for its installation.

Staff at SSEN inspect part of the subsea cable before it is laid. (SSEN/PA)
Staff at SSEN inspect part of the subsea cable before it is laid. (SSEN/PA)

Once the cable is in place on the seabed, a construction support ship equipped with a specialist subsea jet trencher will ensure it is buried at the correct depth – with rocks used to protect the cabling in areas where this trenching process is not possible.

The first phase of the project will see cable laid from Noss Head in Caithness to a point to the east of the Orkney Islands.

The second phase of cabling, which is expected to start in March, will see 57km of cable laid heading south from Weisdale Voe on Shetland.

The third phase, due to take place later in 2023, will then see further cables laid to link these, creating the full 260km subsea HVDC link.

SSEN Transmission lead project manager Chris Finnigan said: “We are delighted that specialist cable-laying vessel NKT Victoria has begun this major milestone in kicking off the first subsea cable installation campaign on the Shetland HVDC link.

“The installation of the subsea cable is one of the major components of the Shetland HVDC link project, and it marks an exciting step in the project for SSEN Transmission and our contractors, and we look forward to the completion of this first subsea cable campaign over the coming weeks.”